GAO Reminds Offerors Excluded from a Competitive Range to Request a Pre-Award Debriefing

April 24, 2019

WHAT: GAO’s recently issued decision in B-417431, Loc Performance Products, Inc., revived a rarely invoked rule that has a significant impact on the rights of contractors excluded from a competitive range to challenge that exclusion. In Loc, after excluding the contractor from the competitive range, the agency gave the contractor a choice between a pre- or post-award debriefing. The contractor chose a post-award debriefing, during which it first learned why it had been excluded. After receiving its debriefing, the contractor filed a protest at GAO and challenged the agency’s decision to exclude it from the competitive range. GAO dismissed the protest, finding that it was untimely. GAO held that where an offeror is offered a pre-award debriefing but elects to delay its debriefing, the offeror has failed to diligently pursue its protest. Because the protester would have learned of its protest grounds during the pre-award debriefing, any protest challenging such flaws in the evaluation is untimely.

WHEN: GAO’s decision was issued April 23, 2019.

WHAT DOES IT MEAN FOR INDUSTRY: Contractors that have been excluded from a competitive range should always request a pre-award debriefing. Although the FAR cautions offerors that delaying a debriefing until after award “could affect the timeliness of any protest,” GAO’s decision in Loc reaffirms a decade-old rule that essentially bars post-award competitive range protests if the offeror was offered either a pre- or post-award debriefing but elected a post-award debriefing. This is true even where the agency seems to suggest that a post-award debriefing would be better: in Loc, after the offeror requested a pre-award debriefing, the agency responded by explaining that the offeror would receive different information in a post-award debriefing, and clarified that the offeror could choose either a pre- or post-award debriefing. Unsurprisingly, this exchange changed the offeror’s mind about choosing a pre-award debriefing, but GAO was unsympathetic.

To preserve all protest rights, a contractor excluded from a competitive range should request a pre-award debriefing within three days of receiving notice of exclusion; and accept the first date of the debriefing offered. If the agency declines to provide a pre-award debriefing, a protest after a required post-award debriefing will still be timely.

This course of action will ensure the contractor retains the ability to timely file a protest or to obtain a stay.

Read Time: 2 min
Jump to top of page

Wiley Rein LLP Cookie Preference Center

Your Privacy

When you visit our website, we use cookies on your browser to collect information. The information collected might relate to you, your preferences, or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. For more information about how we use Cookies, please see our Privacy Policy.

Strictly Necessary Cookies

Always Active

Necessary cookies enable core functionality such as security, network management, and accessibility. These cookies may only be disabled by changing your browser settings, but this may affect how the website functions.

Functional Cookies

Always Active

Some functions of the site require remembering user choices, for example your cookie preference, or keyword search highlighting. These do not store any personal information.

Form Submissions

Always Active

When submitting your data, for example on a contact form or event registration, a cookie might be used to monitor the state of your submission across pages.

Performance Cookies

Performance cookies help us improve our website by collecting and reporting information on its usage. We access and process information from these cookies at an aggregate level.

Powered by Firmseek