OMB Tells Agencies to Be Flexible When Managing Contracts in the Time of COVID-19

March 24, 2020

WHAT: As the novel coronavirus (COVID-19) continues to significantly impact day-to-day life, federal contractors have been seeking guidance from agencies on how COVID-19 will affect their contracts. On Friday, March 20, 2020, the Office of Management and Budget (OMB) issued a memorandum to the heads of executive departments and agencies to address the management of federal contract performance issues associated with COVID-19. The memo urges agencies to be flexible in allowing contractors to telework and asks agencies to allow extensions for those contracts that cannot support flexible work arrangements. The memo also reminds agencies of the emergency procurement authorities that are available under the Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), including increasing the micro-purchase and simplified acquisition thresholds to allow for quicker procurements. Finally, the memo includes responses to “Frequently Asked Questions” about teleworking, mitigating the impact of COVID-19 on contractors, contractor requests for equitable adjustment (REAs), increasing flexibility in procurement activities, and tracking contract spending related to COVID-19.

In answering a question about responding to contractor requests for equitable adjustments (REAs), OMB encourages agencies to consider REAs on a case-by-case basis, taking into account, among other factors, whether the requested costs are allowable and reasonable. The memo provides examples of what a prudent contractor would do in the face of COVID-19 that may result in the incurrence of costs: take actions consistent with the Centers for Disease Control and Prevention (CDC) guidance and reach out to the contracting officer to discuss appropriate actions. Importantly for certain service contractors, the memo suggests that agencies should consider REAs for idle labor costs when “it is beneficial to keep skilled professionals or key personnel in a mobile ready state for activities the agency deems critical to national security or other high priorities (e.g., national security professionals, skilled scientists).”

OMB’s memo provides helpful guidance for contracting officers and federal contractors, and is consistent with our prior guidance. Contractors should share the memo with their contracting officers when they are seeking guidance about how the COVID-19 crisis will impact their contracts.

WHEN: The memorandum was issued on March 20, 2020.

WHAT DOES IT MEAN FOR INDUSTRY: The new guidance out of OMB should be encouraging to Federal contractors for many reasons. First, the widespread guidance should help standardize agencies’ responses to performance issues arising out of COVID-19. Second, the memo makes clear that the burden of the impacts of COVID-19 should not fall on the contractor. As we previewed in an earlier alert, a number of contract clauses may provide an excuse for nonperformance and/or allow for an equitable adjustment if COVID-19 impacts contract performance. The memo highlights these clauses and encourages agencies to consider granting REAs if the costs are allowable and reasonable. Third, by taking advantage of flexible work arrangements, Federal contractors can continue to perform and potentially mitigate the need for future requests for extensions or REAs.

Visit our COVID-19 Resource Center

Read Time: 2 min

Practice Areas

Jump to top of page

Wiley Rein LLP Cookie Preference Center

Your Privacy

When you visit our website, we use cookies on your browser to collect information. The information collected might relate to you, your preferences, or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. For more information about how we use Cookies, please see our Privacy Policy.

Strictly Necessary Cookies

Always Active

Necessary cookies enable core functionality such as security, network management, and accessibility. These cookies may only be disabled by changing your browser settings, but this may affect how the website functions.

Functional Cookies

Always Active

Some functions of the site require remembering user choices, for example your cookie preference, or keyword search highlighting. These do not store any personal information.

Form Submissions

Always Active

When submitting your data, for example on a contact form or event registration, a cookie might be used to monitor the state of your submission across pages.

Performance Cookies

Performance cookies help us improve our website by collecting and reporting information on its usage. We access and process information from these cookies at an aggregate level.

Powered by Firmseek